Project ACE, City College, Norwich

Project Description:

 

The project comprised the refurbishment of Blakeney Building (single storey section) to provide a modern

teaching facility to house Advanced Construction and Engineering. 

 

The works included forming new openings for windows and doors to the facades, internal demolition followed by new glazed partitions, external works to adjust levels and create new entrance together with MEP installation throughout.

Key Challenges:

  • Undertaking works on an operational college campus (June/ July 22) including coordination with adjacent building occupiers as needed throughout and dedicated pedestrian routes

  • A significant number of roof lights present across the site area.  All were deemed fragile and robust controls during works in proximity was required to ensure a safe roof access solution during the works and also post completion for end user access for maintenance

 

Should you wish to know more about our role on Educational projects, please contact hello@iM2ltd.com

iM2 Role: Principal Designer

Project Team:

City College, Norwich

MJS Projects (March) Ltd

LSI Architects

Clancy Consulting

Clear Consulting & Design Ltd

Sector: Higher Education

Start Date: June 2022

Completion: September 2022

Value: (£) Confidential

Screenshot 2023-01-03 at 14.59.09.png
Screenshot 2023-01-03 at 14.59.38.png
Screenshot 2023-01-03 at 14.59.16.png
Screenshot 2023-01-03 at 14.59.44.png
APS-logo White.jpg
iirsm_main_logo.jpg
iM2 Limited
Hamilton House
Mabledon Place
London, WC1H 9BB
England, UK
  • X
  • LinkedIn

www.iM2ltd.com

0203 972 4157

CIOB-Logo.jpg
IOSH-Logo.jpg
iM2 LOGO ISSUE A OUTLINES 25-05-20.png
bottom of page